7 December 2006 High Row
|
|


|
|
6 December 2006 French Market
|
|



|
|
21 November 2006 Views from the Clock Tower
|
 |
|
16 November 2006 Blackwellgate
New bench. |
 |
|
16 November 2006 High Row
Laying the roadway at the foot of the High Row steps. |
 |
|
16 November 2006 High Row (North)
Paving at north end of High Row and Prebend Row. |
 |
|
16 November 2006 High Row (opposite clock tower)
Water feature under construction. |
 |
|
16 November 2006 Northgate
Paving complete. |
 |
|
31 August 2006 Blackwellgate
Paving is almost complete on the south section. Works outside Boyes are awaiting final gas main diversion. |
 |
|
31 August 2006 Blackwellgate
Works are ongoing in the life pulse sculpture area. New bus stop has been installed and electrical supply connected. |
 |
|
31 August 2006 High Row
Step foundations have been completed along with two planter foundations. Paving works are ongoing on High Row Works have started on the water feature. |
 |
|
31 August 2006 Northgate
Works are nearing completion on the road pavement. Rising bollard foundations have been installed. |
 |
|
31 August 2006 Tubwell Row
Loading bay on the south side has been substantially complete and is available for use. |
 |
|
06 July 2006 Bondgate
Paving is near to completion on Bondgate with the installation of new cycle racks underway. |
 |
|
06 July 2006 High Row
Foundations for the first of the steps and 2 of the planters on High Row have been completed. Paving has recommenced in this area. |
 |
|
06 July 2006 Tubwell Row
Phase 1 of Tubwell Row has been completed with the installation of a new bus lay-by. |
 |
|
06 July 2006 Tubwell Row
Phase 2 of Tubwell Row has commenced with the excavating of the new old road. |
 |
|
06 July 2006 Northgate
Work has commenced on lower Northgate with the laying of the new kerb and channel line. The area from Crown Street to Prospect Place is to be closed to traffic on the 10th July for up to 3 months to enable work to be completed more quickly. |
 |
|
06 July 2006 Blackwellgate
Paving has commenced on the South side of Blackwellgate. |
 |
|
13 June 2006 Northgate
The first phase in Northgate has been completed. The second phase lower down in Northgate is just commencing. |
 |
|
13 June 2006 Prebend Row
Work is commencing on Prebend Row for the construction of the new paving. |
 |
|
13 June 2006 Bondgate
Work is nearing completion on the north footpath on Bondgate. |
|

|
|
13 June 2006 High Row
The first steps are laid on High Row, in between the planters. |
 |
|
13 June 2006 Blackwellgate
The North side of Blackwellgate has now been planed and the drainage is being installed. |
 |
|
07 June 2006 High Row
Foundations are laid for the granite planters on High Row. |
 |
|
07 June 2006 Bondgate
Bondgate has been unveiled. |
 |
|
19 May 2006 Blackwellgate
Paving around the bollards on Blackwellgate is underway.
|
 |
|
19 May 2006 Prebend Row & High Row
The gas main has now been completed and the trenches have been filled in, ready for new paving. |
 |
|
19 May 2006 Northgate
Work has commenced on Northgate. |
 |
|
17 March 2006 Blackwellgate
The middle section of Blackwellgate has been completed and is now open to pedestrians. |
 |
|
17 March 2006 Blackwellgate
The paving in front of Binns is well underway. |
 |
|
17 March 2006 Bondgate
Phase 1 of Bondgate is open to pedestrians and is very near to completion. |
 |
|
17 March 2006 Bondgate
Paving has commenced in front of the shop in Bondgate. Part of the paving of Phase 2 has been completed. |
 |
|
17 March 2006 High Row
Phase 1 of the gas diversion has started in High Row. |
 |
|
17 March 2006 High Row
The area between Hallmark and Toni & Guy which has not been affected by the gas diversion has been opened to pedestrians. |
 |
|
17 March 2006 High Row
The gas main diversion works are preventing the work area from being completed. |
 |
|
17 March 2006 Prebend Row
This area is awaiting the gas diversion to be carried out.
|
 |
|
23 February 2006 Blackwellgate
The paving has now been completed on the first section of Blackwellgate, extending from the Newcastle Building Society to Goldsmiths. |
 |
|
23 February 2006 Blackwellgate
The second area on Blackwellgate is well underway. The main area has been constructed with works about to commence outside of Binns. |
 |
|
23 February 2006 Bondgate
Phase 2 of Bondgate has started. The drainage has been installed and the concrete foundation to the road has been cast. Paving is due to commence imminently. |
 |
|
23 February 2006 Bondgate
|
 |
|
23 February 2006 High Row
Works are continuing to the footpath area between Hallmark and Toni & Guy. Gas main diversion works are preventing the work area from being completed. |
 |
|
23 February 2006 High Row
|
 |
|
23 February 2006 Prebend Row
Drainage works are now underway in this area; again the gas diversion is preventing the work area progressing. |
 |
|
23 February 2006 Prebend Row
|
 |
|
30 January 2006 Bondgate
The drainage works have been re-designed in Bondgate to overcome a conflict in location with an existing Gas main. With this issue resolved the paving in the first area is nearing completion. We will be opening this area to pedestrians at the beginning of February.
|
 |
|
30 January 2006 High Row (South)
Northumbrian Water have installed the pipework and connections will be made during at the beginning of February. Works are progressing on High Row with the paving commencing on the higher level. |
 |
|
30 January 2006 Prebend Row
The area has been planed to remove the asphalt and a larger planer removed the existing concrete foundation. Drainage works are then due to commence followed by electrical ducting.
|
| [image not available] |
|
22 Dec 2005 Blackwellgate
Existing roadway has been removed along with general site clearance. Drainage has been installed and the Manhole Connection was completed on 1st Dec by NWL’s contractor. The first section of concrete foundation has been cast. Kerb laying has commenced.
|
| [image not available] |
|
22 Dec 2005 Bondgate
Existing roadway and concrete slab foundation has been removed. Drainage has been installed and connected. The foundation has been concreted overlaying existing concrete in places. 108m² of paving has been laid and grouted on Bondgate.
|
| [image not available] |
|
22 Dec 2005 High Row
Northumbrian Water has installed the pipework and connections will be made after Christmas. The temporary crossover ramp has been constructed in preparation for the works in the New Year. |
|
|
|
|
|
|
|
|
|