| 2004 |
Jan-Mar |
Key stakeholder consultations with shop owners and businesses, Town Centre Board, bus operators, Darlington Association on Disability, emergency services; taxis, Post Office, etc. |
|
Jun |
Advertisement for Contractors Involvement. |
|
Jul |
4-day Public Consultation – viewing of concept designs and materials. |
|
Jul-Oct |
Key stakeholder detailed consultation. |
|
Oct-Dec |
Early Contractual Involvement (ECI), production of construction information and detailed design process. |
|
Nov-Dec (+Jan 2005) |
Traffic Regulation Order Process and Phase One tendering process. |
|
Dec |
External funding partners’ final approval of scheme. |
| 2005 |
Feb |
Phase One Enabling works commence on site. |
|
Feb-May |
Phase Two tendering preparation. |
|
Feb-May |
Conservation Area Consent, Listed Building Consent and Planning Applications submitted and determined. |
|
May-Jun |
Tender issued and appointed for the main contractor. |
|
Jul |
Completion of Phase One Enabling works. |
|
Jul-Aug |
Early Contractual Involvement with successful contractor. |
|
Sep |
Enabling works to introduce new traffic management system. |
|
Sep 18 |
New traffic management system commences |
|
Sep 23-25 |
Artistic Event to mark the introduction of the new traffic management system and commencement of main construction works. |
|
Oct |
Enabling works for main construction. |
|
Nov |
Main Public Realm works commence on site at Blackwellgate and Bondgate. |
|
Dec |
2-week break for Christmas. |
| 2006 |
Jan |
Resume Phase Two main Public Realm works. |
|
Feb |
South area of Bondgate unveiled. |
|
Mar |
Upper Northgate west side (from Boots to Primark) commenced. |
|
Mar |
South area of High Row commenced. |
|
May |
North area of Blackwellgate unveiled. |
|
Jun |
East lower Northgate commenced. |
|
Jun |
West upper Northgate complete. |
|
Jun |
South area of Blackwellgate and area close to Skinnergate commenced. |
|
Jul |
North area of Bondgate unveiled. |
|
Jul |
West lower Northgate to commence. |
|
Jul |
South area of Blackwellgate complete. |
|
Jul |
Granite planters to be installed on High Row. |
|
Aug |
Prebend Row to commence. |
|
Oct |
Prebend Row complete. |
|
Nov |
Lower Northgate complete. |
|
Nov |
First of new steps unveiled on High Row. |
|
Nov |
Water cascade features to be installed on High Row. |
|
Dec |
Life Pulse to be installed on Blackwellgate. |
|
Dec |
Blackwellgate complete. |
|
Dec |
Event space revealed. |
|
Dec |
2-week break for Christmas. |
| 2007 |
Jan |
Resume Phase Two main Public Realm works. |
|
Jan |
High Row North to commence. |
|
Jan |
West Row works continue. |
|
Jan |
Upper Northgate works begin. |
|
Feb |
Blackwellgate to West Row corner begins. |
|
Mar |
Upper Northgate complete. |
|
Easter |
Water feature complete. |
|
Easter |
Joseph Pease statue returns. |
|
Easter |
Life Pulse complete. |
|
May |
High Row complete. |
|
Summer |
Completion of Darlington Pedestrian Heart Scheme (anticipated). |
|
|
|
|
|
|
|
|
|