Timescale for the Pedestrian Heart Project

The proposed phasing and programme is anticipated to be:

2004      Jan-Mar Key stakeholder consultations with shop owners and businesses, Town Centre Board, bus operators, Darlington Association on Disability, emergency services; taxis, Post Office, etc.
  
Jun Advertisement for Contractors Involvement.
  
Jul 4-day Public Consultation – viewing of concept designs and materials.
  
Jul-Oct Key stakeholder detailed consultation.
  
Oct-Dec Early Contractual Involvement (ECI), production of construction information and detailed design process.
  
Nov-Dec
(+Jan 2005)
  
Traffic Regulation Order Process and Phase One tendering process.
  
Dec

External funding partners’ final approval of scheme.
     

2005 Feb Phase One Enabling works commence on site.
  
Feb-May Phase Two tendering preparation.
     
Feb-May Conservation Area Consent, Listed Building Consent and Planning Applications submitted and determined.
     
May-Jun Tender issued and appointed for the main contractor.
  
Jul Completion of Phase One Enabling works.
   
Jul-Aug Early Contractual Involvement with successful contractor.
  
Sep Enabling works to introduce new traffic management system.
  
Sep 18 New traffic management system commences
  
Sep 23-25

Artistic Event to mark the introduction of the new traffic management system and commencement of main construction works.
  

Oct Enabling works for main construction.
  
Nov
    
Main Public Realm works commence on site at Blackwellgate and Bondgate.
 
Dec 2-week break for Christmas.
  
2006 Jan Resume Phase Two main Public Realm works.
  
Feb South area of Bondgate unveiled.
 
Mar Upper Northgate west side (from Boots to Primark) commenced.
 
Mar South area of High Row commenced.
 
May North area of Blackwellgate unveiled.
 
Jun East lower Northgate commenced.
 
Jun West upper Northgate complete.
 
Jun South area of Blackwellgate and area close to Skinnergate commenced.
 
Jul North area of Bondgate unveiled.
 
Jul West lower Northgate to commence.
 
Jul South area of Blackwellgate complete.
 
Jul

Granite planters to be installed on High Row.
 

Aug Prebend Row to commence.
 
Oct Prebend Row complete.
 
Nov Lower Northgate complete.
 
Nov First of new steps unveiled on High Row.
    
Nov Water cascade features to be installed on High Row.
 
Dec Life Pulse to be installed on Blackwellgate.
 
Dec Blackwellgate complete.
    
Dec Event space revealed.
  
Dec 2-week break for Christmas.
  
2007 Jan Resume Phase Two main Public Realm works.
  
Jan High Row North to commence.
  
Jan West Row works continue.
  
Jan Upper Northgate works begin.
  
Feb Blackwellgate to West Row corner begins.
  
Mar Upper Northgate complete.
  
Easter Water feature complete.
  
Easter Joseph Pease statue returns.
  
Easter Life Pulse complete.
  
May High Row complete.
 
Summer Completion of Darlington Pedestrian Heart Scheme (anticipated).
  
                      

Last updated - 25/01/2007