Roadworks Report

Community Services Department

Tel: (01325) 388799

Below are details of works which it is anticipated could cause disruption. For access to the full Street Works Register click here.

Location/DescriptionStart DateDurationTraffic ManagementOrganisation

Hurworth Road, Neasham, Darlington

Construct carriageway system, lay kerbs and patch the carriageway

13/10/0814 weeksMulti - Way Traffic LightsDBC Highway Maintenance

ADVANCE NOTICE - B6280 Coniscliffe Road/ Carmel Road, Darlington

New gas main

20/10/084 weeksCarriageway restrictionsNorthern Gas Networks

ADVANCE NOTICE - Middleton Road/ Sadberge Road, from the junction at the A67 Yarm Road roundabout northwards to the south side of the slip road to the A66

Carriageway deep patching

20/10/082 weeksRoad closure. A diversion will be signed.DBC Highway Maintenance

Whessoe Road/ Longfield Road junction, Darlington

Works to BT cable

14/10/083 days3 Way Traffic LightsBT

A68 Woodland Road to Pierremont Crescent, Darlington o/s 181

Gas main diversion for NWL

24/07/0819 weeksFootpath restrictionsNorthern Gas Networks for NWL

Pierremont Crescent, Darlington between Woodland Road and Milbank Road

Major sewer works

06/10/0825 weeksRoad closed for 70 metres at any one timeNorthumbrian Water Ltd

Whessoe Road Darlington, Whessoe Cottages for a distance of 200m south bound

New electricity supply

06/10/082 weeks2 Way Traffic Lights 09:00 - 16:00Northern Electric Distribution Ltd

Westfield Drive, Hurworth

Footpath refurbishment

22/09/084 weeksFootpath restrictionsDBC Highway Maintenance

B6279 Staindrop Road, Darlington from o/s 2 to Mowden PH

New gas main & connections

07/07/0816 weeks2 Way Traffic Lights as requiredNorthern Gas Networks

A68 Burtree Interchange

Bridge works

25/03/08Until early NovemberSouth bridge closed overnight. Traffic diverted onto north bridge. Note change to traffic management layout from 17 AugCarillion for A-one