Feethams Office Development- Plot 1

Reference Number: 0733
Department: Economic Growth
Date Added: 03 July 2017
Last Updated:

Contact Officer Details

Name: Guy Metcalfe
Email: Guy.Metcalfe@darlington.gov.uk
Telephone: 01325 406725

Lead Scrutiny Committee and Chair:

Committee: Efficiency and resources scrutiny committee
Scrutiny Chair: Councillor I G Haszeldine
Email: Ian.Haszeldine@darlington.gov.uk
Lead Officer: Elizabeth Davison
Lead Officer Email: Elizabeth.Davison@darlington.gov.uk

Relevant Cabinet Members

Name Email Portfolio
Chris McEwan chris.mcewan@darlington.gov.uk Economy and Regeneration Portfolio
Stephen Harker stephen.harker@darlington.gov.uk Deputy Leader of the Council and Efficiency and Resources Portfolio

Description of Decision to be Taken:

Update Cabinet on the feasibility work undertaken in respect of the Council’s proposals to construct a 3000 sq. ft. Grade A offices block. To seek authority to progress outline design details to RIBA Stage 3.Note that capital funding of up to £8.5 M may be required.

Action: Update and decision
Date to be considered by Cabinet: 11 July 2017
Date to be considered by Council:
Deferred: No
Deferral History:

Reason for late inclusion:

Waiting for the feasibility report and the extent of the Council’s initial commitment.

Added to the plan in accordance with:

General Exception Rule: Yes

Other Details

Affected Wards: Park East Ward
Documents to be submitted: Report and appendices
Proposed Consultees: None
Consultation Method: N/A