Tees Valley Joint Minerals and Waste Local Plan Timetable
This Tees Valley Joint Minerals and Waste Local Plan Timetable is published in accordance with Regulation 9 of the Town and Country Planning (Local Planning) Regulations (2026) and shall have effect from 23 October 2026.
It sets out the timetable for the emerging Tees Valley Joint Minerals and Waste Local Plan which will apply to the Borough Councils of Darlington, Hartlepool, Middlesbrough, Redcar and Cleveland (excluding land within the North York Moors National Park) and Stockton-on-Tees (“the Councils”).
In accordance with the regulations, the timetable will be reviewed monthly and at key milestones. It will be updated when necessary.
The Tees Valley Joint Minerals and Waste Local Plan will be a single document which will:
· guide future growth and development of minerals and waste across the five boroughs;
· set out policies on matters relating to the future development minerals and waste on land within the boroughs; and
· replace the current Tees Valley Joint Minerals and Waste Core Strategy Development Plan Document and Polices and Sites Development Plan Document (2011).
Matters that do not relate to minerals and waste will be deal with through each borough’s Local Plan.
The Joint Minerals and Waste Local Plan will be prepared in accordance with the Planning and Compulsory Purchase Act (2004), as amended, and the Town and Country Planning (England) Local Planning Regulations (2026).
Timetable for the Tees Valley Joint Minerals and Waste Local Plan
|
Activity |
Indicative start date |
|
Notice of intention to commence local plan preparation |
23rd October 2026 |
|
Scoping consultation starts |
24th November 2026 |
|
Scoping consultation ends |
8th January 2027 |
|
Publication of Gateway 1 self-assessment |
30th April 2027 |
|
Plan preparation period |
31st May 2027 – 30th March 2029 |
|
Consultation on proposed local plan content and evidence starts |
17th September 2027 |
|
Consultation on proposed local plan content and evidence ends |
29th October 2027 |
|
Gateway 2 Submission |
30th November 2027 |
|
Consultation on proposed local plan starts |
15th October 2028 |
|
Consultation on proposed local plan ends |
10th December 2028 |
|
Gateway 3 Submission |
30th March 2029 |
|
Submit plan for examination |
30th April 2029 |
|
Adoption |
31st October 2029 |